TimeMap supports a variety of date formats when adding fact boxes to timelines.
TimeMap supports the following date formats:
• | Complete dates (8/1/00) |
• | Dates and times (8/1/00 5:25 p.m.) |
• | Partial dates and times (8/??/00 5:?? p.m.) |
• | Date and time ranges (8/1/00 5:15 p.m. to 8/1/00 5:19 p.m.) |
When you enter a date range, TimeMap's default behavior is to mark both the begin date and the end date on the time scale.
When entering dates, consider the following:
Example: 99 or 3/99 are both valid data entries
Date status options are: ~ Around < Before =< On or Before = On => On or After > After
Example: A fact box dated <08/02/99 is stacked above one dated 08/02/99.
|
When entering times, consider the following:
Example: 3/15/00 6:30 p.m.
Example: 3/15/00 6:?? p.m.
Time status options are: ~ Around < Before =< At or Before = At => At or After > After
Example: A fact box with a date of 01/02/00 < 5:15 p.m. is stacked above one dated 01/02/00 > 5:15 p.m.
|
When entering a date/time range, consider the following:
Example: 3/15/00 to 4/12/00
Example: 3/15/00 5:15 a.m. to 3/16/00 2:14 p.m. You must enter the date twice even if the times are on the same day.
If you want to display a date range in your fact box and have TimeMap only mark the beginning date, clear the Draw Date Range check box in the Fact Box Properties dialog box.
|
|
Once your date format and display settings are selected, you can still make additional text customizations in a fact box. For example, you might have your date format set to the original date below and want to edit the date display to the modified date below as well as a line drop to the date scale for September 15, 2008. Original date: September 15, 2008 Modified date: Mid-September 2008
|
![]() |